System: JPS60FS | Programme: 1 Week | Size: 90m (L) x 10m (H)
During the London 2012 Olympic Games, ExCeL London required a high-performance temporary partition system to separate the Boxing and Fencing competition arenas within its main exhibition hall.
Jumbo Stud Partitions was appointed to design, supply and install a robust acoustic and fire-rated dividing wall capable of performing at the highest level — without any permanent impact on the building structure.
Client: GES (Global Experience Specialists)
Location: ExCeL London, Royal Docks
System Installed: F60S Robust Partition (smooth finish, painted white)
Partition Size: 87 metres long × up to 10 metres high
Fire Rating: 60 minutes
Acoustic Performance: 54 dB
Robustness: Severe Duty Rated
Programme: 7-day maximum build
Completion: Installed in 6 days
The client required a temporary acoustic dividing wall to:
A critical condition set by ExCeL London was that no holes or permanent fixings could be made to the floors, walls, or fabric of the building.
Constructing an 87-metre-long partition up to 10 metres high inside a major Olympic venue — without fixing into the structure — required careful engineering, detailed pre-planning and precise installation.
The system needed to provide structural integrity, acoustic performance and fire resistance while remaining completely non-invasive to the building.
Jumbo Stud Partitions designed and implemented a bespoke fixing method that allowed the head track of the partition to connect securely to existing in-situ sliding gear at high level.
This approach ensured:
The F60S Robust “F” Series partition system was installed with a smooth painted white finish to maintain a clean and professional arena appearance.
All pre-construction planning and coordination ensured the project ran seamlessly.
The installation was completed in 6 days, one day ahead of the maximum 7-day programme — a critical achievement within the Olympic build schedule.
Following the conclusion of the Games, the partition was dismantled and removed efficiently.
The venue was returned to its original condition with no signs of construction or structural alteration, fully meeting the client’s non-invasive requirements.
This project demonstrates Jumbo Stud Partitions’ ability to:
Deliver large-scale temporary partition solutions under extreme time pressures
Engineer innovative non-invasive installation methods
Achieve high acoustic and fire performance standards
Operate successfully within world-class venues and live international events
Jumbo Stud Partitions specialises in engineered acoustic and fire-rated partition systems for complex commercial environments.
The JPS60FS system is engineered for commercial and industrial environments where certified fire protection, acoustic performance, and efficient installation are essential. Designed as a robust steel-framed partition solution, it delivers 60-minute fire resistance while maintaining structural integrity and a high-quality finish.
Its precision-engineered build-up offers a practical, programme-friendly alternative to traditional blockwork, reducing weight, installation time, and on-site disruption without compromising compliance or durability.
This project highlights Jumbo Stud Partitions’ ability to deliver reliable, fire-rated partition systems that combine performance, efficiency, and build certainty — even within high-profile, time-sensitive environments.
If you’re planning a project that demands jumbo stud partition solutions, fire-rated acoustic performance, or extreme heights, we’re ready to help.
📞 Call: 01425 472748
🌐 www.jumbostudpartitions.co.uk
📧 Contact us to discuss your requirements
| Cookie | Duration | Description |
|---|---|---|
| cookielawinfo-checkbox-analytics | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Analytics". |
| cookielawinfo-checkbox-functional | 11 months | The cookie is set by GDPR cookie consent to record the user consent for the cookies in the category "Functional". |
| cookielawinfo-checkbox-necessary | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookies is used to store the user consent for the cookies in the category "Necessary". |
| cookielawinfo-checkbox-others | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Other. |
| cookielawinfo-checkbox-performance | 11 months | This cookie is set by GDPR Cookie Consent plugin. The cookie is used to store the user consent for the cookies in the category "Performance". |
| viewed_cookie_policy | 11 months | The cookie is set by the GDPR Cookie Consent plugin and is used to store whether or not user has consented to the use of cookies. It does not store any personal data. |