At the Johnsons Cars Volkswagen dealership in Otium Park, Solihull, our team delivered a specialist internal partitioning installation using a combination of JPS60FS and JPS30FS Jumbo Partition Systems. The works formed part of the construction of a modern automotive showroom and workshop facility, requiring robust fire-rated partitions to separate operational areas while maintaining a clean internal finish suitable for a commercial environment.

Project Overview

The project required a number of full-height internal partitions designed to provide both fire protection and acoustic separation across the building. The main compartment wall was constructed as a 60-minute fire-rated partition, while additional 30-minute fire-rated partitions were installed to divide workshop, office and service areas within the facility.

The primary fire wall (Wall A) extended approximately 48.5 linear metres, forming a major fire compartment within the building. A secondary wall (Wall B) delivered 30-minute fire separation across approximately 54 metres, including a 10.3 metre bulkhead section to accommodate changes in the internal layout.

Key Project Details

  • Project: Internal Fire-Rated Partitions
  • Location: Johnsons Cars Volkswagen, Otium Park, Solihull
  • Main Contractor: MCS Group
  • Partition Systems:
  • Fire Ratings:
    • 60 minutes (Integrity & Insulation)
    • 30 minutes (Integrity & Insulation)
  • Acoustic Performance:
    • Up to 54dB for the JPS60FS system
    • Approximately 43dB for the JPS30FS system
  • Partition Lengths:
    • 48.5 metres – 60-minute fire wall
    • 54 metres + 10.3m bulkhead – 30-minute wall

Finish: Smooth painted finish ready for decoration.

Installation Approach

Both partition systems were constructed using heavy-duty galvanised steel stud frameworks combined with high-performance board linings designed to achieve the required fire and acoustic ratings.

Key construction elements included:

  • 150mm steel stud framework installed at 600mm centres
  • 12.5mm high-performance boards fixed to both sides of the partition
  • 75mm high-density mineral wool insulation within the wall cavity
  • Deep base and head channel sections providing structural stability
  • A smooth painted finish, achieved through joint treatment, fine surface preparation and two coats of emulsion.

This construction method ensured the partitions delivered both structural strength and the required fire performance while maintaining a clean architectural appearance throughout the facility.

JUMBO STUD WALL Built for the London Olympic Games 2012 - 9
JUMBO STUD WALL Built for the London Olympic Games 2012 - 1
JUMBO STUD WALL Built for the London Olympic Games 2012 - 2
JUMBO STUD WALL Built for the London Olympic Games 2012 - 4
Installed Commissioned And Certified By Jumbo Stud Partition Systems

Project Outcome

The completed installation provides reliable fire compartmentation between workshop, showroom and operational areas, supporting the building’s fire safety strategy while maintaining a professional internal environment.

By combining JPS60FS and JPS30FS Jumbo Partition Systems, the project achieved a flexible and cost-effective partitioning solution capable of meeting different fire performance requirements across the building.

This project highlights how JPS Jumbo Partition Systems can be successfully integrated into complex commercial developments, delivering fire safety, acoustic performance and a high-quality finish in demanding environments such as automotive showrooms and service facilities.

Why JPS30FS?

The JPS30FS system is engineered for commercial and industrial environments where certified fire protection, acoustic performance, and efficient installation are essential. Designed as a robust steel-framed partition solution, it delivers 30-minute fire resistance while maintaining structural integrity and a high-quality finish.

Its precision-engineered build-up offers a practical, programme-friendly alternative to traditional blockwork, reducing weight, installation time, and on-site disruption without compromising compliance or durability.

This project highlights Jumbo Stud Partitions’ ability to deliver reliable, fire-rated partition systems that combine performance, efficiency, and build certainty — even within high-profile, time-sensitive environments.

🏗️ Discover more Jumbo Stud Wall Partitioning Projects

Speak to the Experts

If you’re planning a project that demands jumbo stud partition solutions, fire-rated acoustic performance, or extreme heights, we’re ready to help.

📞 Call: 01425 472748
🌐 www.jumbostudpartitions.co.uk
📧 Contact us to discuss your requirements